Acquiring the requirement(1 day)
Lighting sources such as type of led, led manufacturer
Optical requirements
Mechanical requirements

Evaluation(1 day)
Ensure the optical solution is feasible
Analysis
Cost analysis for both tooling and lens

Design(3 to 5 days)
Export report of optical design
Export lES file and lighting simulation file such as DLIAUX file.
DFM of the mechanics export

Prototype (7 day)
Tooling manufacture(25 to 30 days)
Export a schedule to the tooling manufacture
Update schedule to customer every week

Validation
Export a report of critical size inspection to the sample
Samples or prototype will be delivered
Optical measurement and simulation

Delivery
The hard tools will be delivered to production
Export PPAP files
Mass production